New onsite training at Dounreay

Work continues at the decommissioned Dounreay Nuclear Site with a team set to be on site this month. AJE has been working at the site handling cladding on the west wall of the PFR turbine hall building.

However, the team is now about to start on the north wall but this time will be trained to use ‘mast climbers’ instead of scaffolding.

Project manager, Allan Martin explained: “We have built up a good reputation at Dounreay, hence why we have now been given the north wall which involves repairing and replacing 1600 sqm of cladding. We will also be replacing all the hot rolled steel cladding rails as they are in an unserviceable condition.”

He added: “We have previously used scaffolding on site, but this can be quite labour intensive, so we are hiring in mast climbers with the team being given on-site training when the project begins. We expect the project to last until around November and are close to being awarded the contract for the next phase of the works.”